EQS-News: Quarterly Activities Report for the period ending 31 March 2026
|
EQS-News: Vulcan Energy Resources Limited
/ Key word(s): Quarterly / Interim Statement
Quarterly Activities Report for the period ending 31 March 2026 Highlights from the Quarter With its €2.2 billion ($AU3.9 billion) financing package secured for its flagship Lionheart Project (Lionheart) in Germany’s Upper Rhine Valley, Vulcan Energy Resources Limited (ASX: VUL) (Vulcan Energy or the Company) has made good progress in its construction activities.
Project Lionheart Lionheart involves the construction of an integrated lithium and renewable energy project targeting production capacity of 24,000 tonnes of lithium hydroxide monohydrate (LHM), enough for ca. 500,000 electric vehicle batteries per annum, with a co-product of 275 GWh of renewable power and 560 GWh of heat per annum for local consumers, over an estimated 30-year project life[1]. Lionheart represents the first phase of planned production, with future phases also in progress across the Upper Rhine Valley Brine Field. Health and Safety
Corporate
Subsequent Events
Managing Director and CEO, Cris Moreno, commented: “Vulcan has had a great start to the year as we deliver against the planned execution programme for our flagship Lionheart Project. “Encouragingly, the lithium market continues going from strength to strength with the need for domestic energy security and critical materials resilience increasingly in focus with government and industry partners. “Driven by accelerating lithium demand from the electrification of mobility, rapid growth in battery storage for artificial intelligence and data centres and the expanding renewables sector, the tailwinds supporting Vulcan are significant. We intend to move at pace to ensure the Company captures this momentum.”
Figure 1: Diagram showing Vulcan business segments that depicts the flow of molecules from upstream to downstream and the various goods and services generated for various applications.
Figure 2: Sunset at the LSC-1 production well site near Landau.
Drilling of Production/ Re-injection Wells
Figure 3: Construction works at the fourth production site ahead of mobilisation of the V10 rig in H2 2026. Figure 4: Overview map of Vulcan’s Lionheart Project
The Company’s combined geothermal and lithium extraction facility has been designed to produce both renewable geothermal energy and lithium chloride (LiCl) from deep geothermal brine. The commercial site, sitting on approximately 10 hectares, is under construction in the Messegelände Südost D12 industrial park in Landau (D12). The second existing Vulcan geothermal plant at Insheim comprises operating wells and produces renewable power that is sold to the grid. The Company’s wells produce hot brine, which is transported through a network of pipelines and cables from the well sites to the geothermal and lithium extraction facility and back to the well sites for re-injection. Landau is also the home to one of Vulcan’s existing geothermal plants which comprises operating wells that generate renewable district heating to the community.
Figures 5 and 6: Equipment arriving for site works at the geothermal and lithium extraction facility in Landau.
The lithium chemicals processing facility (also known as the central lithium plant) will be the Company’s commercial downstream lithium processing hub at Infraserv Park Höchst in Frankfurt, one of Germany’s largest major chemical and energy precincts. The lithium chemicals plant will convert LiCl solution from the lithium extraction facility in Landau into battery‑quality lithium hydroxide monohydrate (LHM), supporting Europe’s push for locally sourced, low‑carbon battery materials. The Company has secured relevant permits to build and operate its lithium chemicals plant for Lionheart, with the facility available for separate growth phases as required.
Figure 7: Infraserv Park Höchst, Frankfurt
Figure 8: Central lithium plant site at Infraserv Park Höchst.
Contracts and procurement
Site activities
Corporate Financing
Future phases Ongoing pre-feasibility study work relating to future phase development continued throughout the reporting period in addition to the following: Mannheim, Germany The Company aims to deliver baseload geothermal heat to stakeholders in the Mannheim region, while simultaneously extracting lithium. Current activities include:
Ludwigshafen, Germany
Regional work in Upper Rhine Valley Brine Field
Additional ASX Disclosure Information Development expenditure of €76.0 million during the quarter primarily related to the progression of the Lionheart Project. This included payments for the supply and installation of the Organic Rankine Cycle (ORC) power plant, land acquisitions of strategic plots (including D12), and advance and milestone payments to major contractors for engineering, procurement and site‑related development activities. Expenditure also included project engineering and procurement activities undertaken to support construction readiness at Lionheart. A detailed breakdown is below:
ASX Listing Rule 5.3.3: Other than the receipt of the lithium production permit for Lionheart (LiThermEx), no licences were acquired or disposed of during the Quarter. For further information see Table 1 below. ASX Listing Rule 5.3.5: Payments to related parties of the Company and their associates during the Quarter per section 6.1 of the Appendix 5B amounted to €413,000. This is comprised of an allocation of the Managing Director remuneration of €129,000, Group Chief Financial Officer and Executive Director remuneration of €107,000, Executive Chair remuneration of €106,000 and Non-Executive Director fees of €71,000. Payments to related parties of the Company and their associates during the quarter per section 6.2 of Appendix 5B were nil. Please see the Remuneration Report in the 2025 Annual Report for further details on Directors’ Remuneration.
Table 1: Vulcan’s integrated lithium and renewable energy project licence table[2]
During the Quarter, there was no change to Vulcan’s Mineral Resource or Ore Reserves.
Daniel Tydde | Company Secretary
Jeremy McManus | Head of Investor Relations | jmcmanus@v-er.eu | +61 422 000 675 Judith Buchan | Head of Corporate Communications | jbuchan@v-er.eu | +61 411 597 326 Please contact Vulcan’s Legal Counsel Germany, Dr Meinhard Grodde, for matters relating to the Frankfurt Stock Exchange listing on mgrodde@v-er.eu
Vulcan Energy (ASX: VUL, FSE: VUL) is building the world’s first integrated carbon neutral lithium and renewable energy business to decarbonise battery production. Located in the Upper Rhine Valley Brine Field between Germany and France, Vulcan’s Lionheart Project (Lionheart) is a lighthouse project for Europe’s energy and critical raw material resilience. Lithium is to be extracted from low impurity geothermal sub-surface brines using Vulcan’s industry-leading VULSORB® technology. Naturally heated, the brine powers production and conversion of lithium to battery-quality material by creating a renewable energy co-product for use in operations, with surplus sold into the local energy market. This integration, technology and favourable brine chemistry collectively enables one of the lowest cost lithium operations globally. Extraction is only the starting point for Vulcan. The Company has reimagined mining using innovation to integrate and capture more of the value chain. The Company has made its positive Final Investment Decision on Lionheart, construction is underway, offtake contracted and further phases of production are in planning. For more information, please go to www.v-er.eu
Some of the statements appearing in this announcement may be in the nature of forward-looking statements. You should be aware that such statements are only predictions and are subject to inherent risks and uncertainties. Those risks and uncertainties include factors and risks specific to the industries in which Vulcan operates and proposes to operate as well as general economic conditions, prevailing exchange rates and interest rates and conditions in the financial markets, among other things. Actual events or results may differ materially from the events or results expressed or implied in any forward-looking statement. No forward-looking statement is a guarantee or representation as to future performance or any other future matters, which will be influenced by a number of factors and subject to various uncertainties and contingencies, many of which will be outside Vulcan’s control. Vulcan does not undertake any obligation to update publicly or release any revisions to these forward-looking statements to reflect events or circumstances after today's date or to reflect the occurrence of unanticipated events. No representation or warranty, express or implied, is made as to the fairness, accuracy, completeness or correctness of the information, opinions or conclusions contained in this announcement. To the maximum extent permitted by law, none of Vulcan, its Directors, employees, advisors or agents, nor any other person, accepts any liability for any loss arising from the use of the information contained in this announcement. You are cautioned not to place undue reliance on any forward-looking statement. The forward-looking statements in this announcement reflect views held only as at the date of this announcement. This announcement is not an offer, invitation or recommendation to subscribe for, or purchase securities by Vulcan. Nor does this announcement constitute investment or financial product advice (nor tax, accounting or legal advice) and is not intended to be used for the basis of making an investment decision. Investors should obtain their own advice before making any investment decision.
The information in this announcement that relates to estimates of Mineral Resources and Ore Reserves is extracted from the Bridging Engineering Study Results announcement on 16 November 2023 (Bridging Study Announcement) and the Future Phase Pipeline – Mannheim Resources Growth announcement on 9 July 2025[5], both of which are available to view on Vulcan's website at http://v-er.eu. Vulcan confirms, that in respect of the estimates of Mineral Resources and Ore Reserves included in this announcement:
The information in this announcement that relates to Exploration Results is extracted from the “Positive start to Phase One Lionheart Project field development” announcement on 19 November 2025 which is available to view on http://v-er.eu 20 Vulcan's website at http://v-er.eu. Vulcan confirms, that in respect of the Exploration Results included in this announcement: a) it is not aware of any new information or data that materially affects the information included in the original market announcement, and that all material assumptions and technical parameters underpinning the Exploration Results in the original market announcement continue to apply and have not materially changed; and b) the form and context in which the Competent Persons' findings are presented in this announcement have not been materially modified from the original market announcement
The information in this announcement that relates to production targets is extracted from the Bridging Study Announcement. Vulcan confirms that all material assumptions underpinning the production targets included in the original market announcement continue to apply and have not materially changed. This announcement contains forecast financial information (including forecast financial information derived from the Company's production targets). This forecast financial information is based on the material assumptions set out in (or referred to in) slide 39 of the Company's ASX announcement titled "Financing and FID presentation" released on 3 December 2025 (Investor Presentation) and the Independent Expert Report included as section 17 to the ASX announcement titled "Information Memorandum" released on 11 December 2024 (Information Memorandum), both of which are available to view on Vulcan's website at http://v-er.eu. Vulcan confirms that those assumptions set out in the ASX announcements referred to above (for the avoidance of doubt, having regard to the extent to which the assumptions referred to in the Information Memorandum have been modified by the updated information set out in (or referred to in) slide 39 of the Investor Presentation) continue to apply and have not materially changed. The Company believes that it has a reasonable basis for making the forward-looking statements in this announcement (including with respect to forecast financial information). [1] Based on the Phase One Lionheart production target capacity of 24kt p.a. from Bridging Engineering Study ASX announcement 16th November 2023 and Vulcan internal estimated average EV battery size and chemistry in Europe. Refer to the Competent Person and Production Targets and Forecast Financial Information Statements within this announcement and the Key Risks in Appendix 3 of the Investor Presentation dated 3 December 2025 regarding the risks associated with resource exploration and development projects. [2] Vulcan’s licences as at the date of this report, unless otherwise noted, with the Lionheart licences shaded in grey. Vulcan has a total of 24 licences, with 21 in Germany. The German licences are over 17 separate areas as Insheim and LiThermex, Landau-Süd and Ilka, Lisbeth and Taro, Flaggenturm and Fuchsmantel are separate lithium and geothermal licences over the same respective areas [3] The receipt of the lithium production permit for Lionheart occurred during the Quarter. [4] The Company notes the decision of the Nancy Administrative Couty of Appeal against the geothermal permit, and for the lithium exploration permit grant validation and will continue to work in consultation with the government and local authorities. [5] The Mannheim Announcement relates solely to the lithium brine Resource estimation for the Mannheim sector.
30.04.2026 CET/CEST Dissemination of a Corporate News, transmitted by EQS News - a service of EQS Group. |
| Language: | English |
| Company: | Vulcan Energy Resources Limited |
| Unit 1, Level 11, 1 Spring Street | |
| WA 6000 Perth | |
| Australia | |
| E-mail: | dtydde@v-er.eu |
| Internet: | www.v-er.eu |
| ISIN: | AU0000066086 |
| WKN: | A2PV3A |
| Listed: | Regulated Market in Frankfurt (Prime Standard); Regulated Unofficial Market in Dusseldorf, Hamburg, Munich, Stuttgart, Tradegate BSX |
| EQS News ID: | 2319236 |
| End of News | EQS News Service |
|
|
2319236 30.04.2026 CET/CEST
Boersengefluester.de (BGFL) provides an overview of the key figures on sales, earnings, cash flow and dividends to help you better assess the fundamental development of the respective companies. All information is entered manually in our database - the source is the respective annual reports. All estimates for future figures are provided by BGFL.
| The most important financial data at a glance | ||||||||
| 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026e | ||
| Sales1 | 0,00 | 3,80 | 3,62 | 6,78 | 8,12 | 7,35 | 0,00 | |
| EBITDA1,2 | 6,90 | -15,80 | -11,69 | -26,32 | -34,67 | -55,29 | 0,00 | |
| EBITDA-Margin3 | 0,00 | -415,79 | -322,93 | -388,20 | -426,97 | -752,26 | 0,00 | |
| EBIT1,4 | -6,80 | -18,43 | -13,99 | -32,19 | -44,27 | -68,68 | 0,00 | |
| EBIT-Margin5 | 0,00 | -485,00 | -386,46 | -474,78 | -545,20 | -934,38 | 0,00 | |
| Net Profit (Loss)1 | -6,73 | -18,85 | -13,45 | -26,96 | -42,36 | -69,58 | 0,00 | |
| Net-Margin6 | 0,00 | -496,05 | -371,55 | -397,64 | -521,68 | -946,60 | 0,00 | |
| Cashflow1,7 | -1,78 | -11,35 | -7,42 | -24,33 | -30,68 | -47,73 | 0,00 | |
| Earnings per share8 | -0,04 | -0,10 | -0,09 | -0,17 | -0,23 | -0,30 | -0,26 | |
| Dividend per share8 | 0,00 | 0,00 | 0,00 | 0,00 | 0,00 | 0,00 | 0,00 | |
1 in Mio. Euro; 2 EBITDA = Earnings before interest, taxes, depreciation and amortisation; 3 EBITDA in relation to sales; 4 EBIT = Earnings before interest and taxes; 5 EBIT in relation to sales; 6 Net profit (-loss) in relation to sales; 7 Cashflow from operations; 8 in Euro; Source: boersengefluester.de
Auditor: RSM
All relevant valuation ratios, dates and other investor information on your share at a glance. Good to know: All data comes from boersengefluester.de and is updated daily. This means you are always up to date. You can get brief explanations of the key figures by moving the cursor or mouse over the relevant field.
| INVESTOR-INFORMATION | ||||||
| ©boersengefluester.de | ||||||
| Vulcan Energy Resources | ||||||
| WKN | ISIN | Legal Type | Marketcap | IPO | Recommendation | Plus Code |
| A2PV3A | AU0000066086 | Ltd. | 1.149,84 Mio € | 15.02.2022 | Halten | |
| PE 2027e | PE 10Y-Ø | BGFL-Ratio | Shiller-PE | PB | PCF | KUV |
| -18,51 | 0,00 | 0,00 | -6,68 | 1,34 | -24,09 | 156,44 |
|
Dividend '2023 in € |
Dividend '2024 in € |
Dividend '2025e in € |
Div.-Yield '2025e in % |
| 0,00 | 0,00 | 0,00 | 0,00% |
| Annual General Meeting | Q1-figures | Q2-figures | Q3-figures | Annual press conference |
| 28.05.2026 | 29.04.2026 | 11.09.2026 | 29.10.2026 | 27.03.2026 |
| Distance 60-days-line | Distance 200-days-line | Performance YtD | Performance 52 weeks | IPO |
| +11,26% | -6,38% | -5,28% | -9,21% | -57,42% |
Founded in 2013 by Gereon Kruse, the financial portal boersengefluester.de is all about German shares - with a clear focus on second-line stocks. In addition to traditional editorial articles, the site stands out in particular thanks to a large number of self-developed analysis tools. All tools are based on a completely self-maintained database for more than 650 shares. As a result, boersengefluester.de produces Germany's largest profit and dividend forecast.